Smart Cities Mission Nears End: 97% Projects Completed Across 100 Cities But Performance Gaps Persist
Nearly 11 years after its launch, India’s flagship Smart Cities Mission has entered the final phase of implementation, with 97 per cent of all sanctioned projects completed. The latest Ministry of Housing and Urban Affairs data (as of March 31, 2026) shows strong overall delivery, yet city-level performance varies sharply.
Launched on June 25, 2015, the Mission targeted 100 cities with area-based development and pan-city technology solutions covering mobility, water, sanitation, energy efficiency, digital governance and public safety.
Key Numbers at a Glance
- Total projects sanctioned: 8,064 worth Rs 1,64,811 crore
- Projects completed: 7,790 (97%) worth Rs 1,56,257 crore
- Remaining projects: 274 worth about Rs 8,554 crore
- Central allocation: Rs 48,000 crore
- Claimed by states/UTs: Rs 47,458 crore (99%)
- Utilised: Rs 46,377 crore (98%)
Top-Performing Smart Cities
Several cities achieved 100% completion, reflecting strong planning and execution:
- Indore: All 231 projects worth Rs 3,751 crore
- Guwahati: All 21 projects worth Rs 755 crore; full utilisation of Rs 490 crore Central funds
- Chandigarh: All 97 projects worth Rs 2,694 crore
- Varanasi: All 117 projects worth Rs 3,342 crore
- Gujarat standouts – Surat (all 87), Rajkot (all 71), Vadodara (all 52); Ahmedabad 69 of 70
- Others: Patna (all 34), Agartala (all 77), Kohima (all 40), Raipur (337 of 342 – highest number completed)
Cities Still Lagging
Despite the national 97% success rate, some urban centres trail:
- Faridabad: 35 of 44
- Greater Warangal: 103 of 119
- Karnal: 105 of 117
- Mangaluru: 98 of 105
- Ludhiana: 74 of 82
- Kavaratti (Lakshadweep): Weakest performer – only 8 of 12 projects completed; just Rs 45 crore utilised against Rs 183 crore sanctioned; completed works valued at only Rs 11 crore
Northeastern cities such as Aizawl (33 of 45), Shillong (10 of 13) and Imphal (23 of 27) also have unfinished works, though many have crossed the 80-90% mark.
From Construction to Sustainability
Although the Mission formally ended on March 31, 2025, the Ministry has directed states to finish pending projects, prepare long-term operation and maintenance plans, and repurpose Special Purpose Vehicles (SPVs). Integrated Command and Control Centres are to continue supporting urban governance and emergency response.
Urban affairs expert Prof K K Pandey of the Indian Institute of Public Administration notes that completing 97% of projects and utilising 98% of Central funds marks a strong execution record. The real test now lies in maintaining these assets, ensuring regular technology upgrades and delivering lasting improvements in service quality and urban resilience.
Cities with stronger institutional capacity finished faster, while remote or administratively constrained locations continue to face challenges. The Smart Cities Mission has largely delivered modern urban infrastructure; the next chapter depends on sustained operation and maintenance by states and local bodies.